DSE has commenced works on Stage 1 or Palm Lake Resorts, Pelican Waters Project in October 2022.
Stage 1 works included the lighting upgrade of Pelican Waters Golf Club, Lighting of the new Driving Range Car Park and Energex URD works.
Location:
Pelican Waters, Sunshine Coast
Client:
Hall Contracting & Palm Lake Works
Duration:
Oct 22 – June 25
Client References:
Hall Contracting
Project Highlights:
Golf Course Car Park Lighting - Complete June 23
Driving Range Car Park Lighting - Complete July 24
Energex Lighting and URD - Complete June 25